experience high rates of inflation, thereby increasing our operating costs in those countries, we may not be able to generate sufficient revenues to offset the effects of inflation, which could materially and adversely affect our business, financial condition, results of operations and cash flows.
Certain of our power plants depend on third-party service providers for O&M and/or asset management services, and we may not be able to control their work as effectively as if we performed these functions.
We contract with third-party service providers for O&M and/or asset management services for certain of our power plants, and we may contract with additional providers in the future to perform such services. Outsourcing these functions involves the risk that third parties may not perform to our standards, may not produce results in a timely manner or may fail to perform at all. Although we have not experienced any significant difficulties with our third-party service providers, it is possible that we could experience difficulties in the future. Certain of our power plants located in Brazil, India, South Africa and Uruguay utilize third-party service providers for O&M and/or asset management services. If these third-party service providers default on their contractual obligations to us it may: (i) cause us to default in our regulatory obligations; (ii) adversely impact the ongoing operation of our power plants; and/or (iii) temporarily reduce our capacity to generate power. Certain of our power plants may encounter difficulties in transitioning O&M and/or asset management services from the existing service provider to us or to a new third party provider, which may have a material adverse effect on the business results of our operations and performance.
Our power plants are exposed to curtailment risks, which may reduce the return to us on those investments and adversely impact our business, financial condition, and results of operations.
Certain of our power plants’ generation of electricity may be curtailed without compensation due to transmission limitations or limitations on the electricity grid’s ability to accommodate intermittent electricity generating sources, reducing our revenues and impairing our ability to capitalize fully on a particular assets potential.
For example, our Honiton wind power plants in China have experienced significant curtailment due to grid constraints, overcapacity, and falling consumer demand. Approximately 29% of potential power generation was curtailed in 2015, and approximately 40% of potential power generation was curtailed in 2016, compared to an original forecast of 21%. We expect the increased curtailment will be partially offset by enlisting eligible sites into a market trading program, which allows the power plants to sell a certain amount of power at a discounted rate. Additionally, our wind power plants in Brazil have a contracted capacity that is slightly lower than their installed capacity, as a result of which the power plants are curtailed during periods of high wind speeds in order not to surpass their contracted power. However, the loss of generation capacity due to such curtailment is generally low, and the excess of capacity generated by some turbines may be offset against the lost capacity from wind turbines that are out of service for maintenance or other reasons. There may also be extraordinary events affecting the transmission grid that may reduce the capacity of the grid, causing the curtailment of power generation. Solutions to ameliorate or eliminate curtailment with respect to our power plants may not be available or may not be effective or may be cost prohibitive to undertake and implement. Curtailment at levels above our expectations could have a material adverse effect on our business, financial condition and results of operations and cash flows and our ability to pay dividends to holders of our Class A common stock.
There are substantial risks associated with the acquisition of renewable energy power plants.
The acquisition of renewable energy power plants is subject to substantial risk, including the failure to identify material problems during due diligence (for which we may not be indemnified post-closing), the risk of over-paying for assets (or not making acquisitions on an accretive basis), the ability to obtain or retain customers and, if the power plants are in new markets, the risks of entering markets where we have limited experience. While we perform due diligence on prospective acquisitions, we may not be able to discover all potential operational deficiencies in such power plants. As detailed in “The SunEdison Bankruptcy has resulted in project defaults that may entitle the related lenders to demand repayment, enforce their security interests or other remedies or restrict the ability of the project companies to make distributions” above, the SunEdison Bankruptcy and its constrained liquidity further exposes us to risk in power plants where SunEdison was the EPC contractor or guarantor. For instance, we may learn of statutory liens asserted by subcontractors against power plants where SunEdison was the EPC contractor or guarantor, and our ability to recover against SunEdison in respect of payments made to such subcontractors to discharge those liens will likely be limited. In addition, our expectations for the operating performance of newly constructed power plants as well as those under construction are based on assumptions and estimates made without the benefit of operating history. However, the ability of these power plants to meet our performance expectations is subject to the risks inherent in newly constructed power plants and the construction of such facilities, including, but not limited to, degradation of equipment in excess of our expectations, system failures and outages. Future acquisitions may not perform as expected or the returns from such acquisitions may not support the financing utilized to acquire them or maintain them. Furthermore, integration and consolidation of acquisitions requires substantial human, financial and other resources and may


45