enrichment relating to the failure by the SunEdison Defendants to transfer the equity interests in the 425 MW India Projects for which the Company paid $231.0 million in the fourth quarter of 2015. The complaint seeks various forms of relief, including a constructive trust upon the equity interests of SunEdison in the 425 MW India Projects, money damages from the defendants, restoration of the $231.0 million to the Company and such other relief as the court may deem just and proper. The claims against the SunEdison Defendants have been stayed as a result of the SunEdison Bankruptcy. The individual defendants filed an answer to the complaint on June 30, 2016.
As previously described, the Third Party Sale Transaction is being conducted in connection with SunEdison’s bankruptcy process and includes the 425 MW India portfolio. The Company has agreed not to pursue claims against a third party buyer, however the Company has retained all of its claims against SunEdison and its affiliated persons.
On September 25, 2016, the Company filed its initial proof of claim in the SunEdison Bankruptcy case, and file an amended proof of claim on October 7, 2016. As set forth in the proofs of claim, the Company believes it has unsecured claims against SunEdison that it estimates are in excess of $2.0 billion. These claims include, without limitation, claims for damages relating to breach of SunEdison's obligations under the sponsorship arrangement between the Company and SunEdison and other agreements; contribution and indemnification claims arising from litigation; claims relating to SunEdison’s breach of fiduciary, agency and other duties; and claims for interference with and the disruption of the business of the Company and its subsidiaries, including the loss of business opportunities, loss of business records, failure to provide timely audited financials, and the increased cost of financing and commercial arrangements. Many of these claims are contingent, unliquidated and/or disputed by SunEdison and other parties in interest in the SunEdison Bankruptcy case, and the estimated amounts of these claims may change substantially as circumstances develop and damages are determined. In addition, recoveries on unsecured claims in the SunEdison Bankruptcy case are expected to be significantly impaired.
Other Matters
From time to time, the Company is a party to legal proceedings arising in the ordinary course of its business. Although the Company cannot predict with certainty the ultimate resolution of such proceedings or other claims asserted against us, except as otherwise described above, the Company does not believe that any other currently pending legal proceeding to which the Company is a party will have a material adverse effect on its business, financial condition or results of operations.

18. RELATED PARTIES
SunEdison Bankruptcy
On April 21, 2016, SunEdison and certain of its domestic and international subsidiaries voluntarily filed for protection under Chapter 11 of the U.S. Bankruptcy Code (the “SunEdison Bankruptcy”). The Company is not a part of the SunEdison Bankruptcy and does not rely substantially on SunEdison for funding or liquidity. The Company continues to participate actively in the SunEdison Bankruptcy proceedings, and the SunEdison Bankruptcy will continue to have a negative impact on the Company given our complex relationship with SunEdison.
During the SunEdison Bankruptcy, SunEdison has not performed substantially as obligated under its agreements with us, including under the Sponsorship Arrangement put in place at the time of the Company’s IPO and certain O&M and asset management arrangements. The Company believes that the Sponsorship Arrangement comprises a single integrated transaction. The agreements comprising the Sponsorship Arrangement are set forth in separate documents and discussed individually in this annual report. However, the elements of the Sponsorship Arrangement are closely related and a default under one element may be a defense to, or excuse performance under, another element. SunEdison and its various stakeholders have expressed disagreement with this view of the Sponsorship Arrangements and can be expected to contest any such assertion in connection with the SunEdison Bankruptcy.
The Company is currently engaged in settlement discussions with SunEdison to resolve, among other issues, intercompany claims and defenses. While these settlement discussions remain ongoing and there can be no guaranty that a settlement will be reached, the Company believes that a successful settlement could facilitate the Company’s exploration of strategic alternatives. Any settlement would be subject to the approval of the bankruptcy court in the SunEdison Bankruptcy.
Our relationship with SunEdison, the ongoing SunEdison Bankruptcy, the delay of this Form 10-K for the year ended December 31, 2015, our delayed Forms 10-Q for the quarters ended March 31, June 30 and September 30, 2016 and the conditions in the capital markets for our corporate level debt and equity securities have increased uncertainty and heightened some of the risks we face. Other aspects of the markets relevant to our business have remained relatively stable, including the expected performance of our power plants, long-term offtake agreements, and the credit quality of our offtakers. We have adjusted our plans and priorities in light of these developments according to our comprehensive contingency plan. While we