(5) The remaining equity interests in NSM Suryalabh, NSM Sitara and NSM L’Volta that were not owned by the Company as of December 31, 2015 were transferred to the Company in April 2016.
(6) The remaining equity interests in Focal, 11% of the equity interests in Millenium and 26% of the equity interest in Azure that were not owned by the Company as of December 31, 2015 were transferred to the Company in the fourth quarter of 2016.

Recent Developments
SunEdison Bankruptcy
As discussed in “Business,” “Risk Factors,” “Management’s Discussion and Analysis of Financial Condition and Results of Operations” and other sections of this annual report, including our audited consolidated financial statements and the notes thereto contained in this annual report, we currently depend significantly on SunEdison for operational, systems and staffing support, among other things. While we continue to evaluate SunEdison’s filings and will continue to monitor the conduct of the bankruptcy proceedings and work to assert and enforce any claims that we may have against SunEdison through those proceedings, the SunEdison Bankruptcy may have a material adverse effect on the Company given our reliance on SunEdison. No assurance can be given on the outcome of the SunEdison Bankruptcy or its impact on the Company. Our Corporate Governance and Conflicts Committee (the “Conflicts Committee”) is responsible for oversight and approval of the business and affairs of the Company relating to or involving SunEdison and any of its affiliates (other than the Company), including in connection with the SunEdison Bankruptcy. The matters described in this section entitled “SunEdison Bankruptcy” and other matters that presented conflict of interest issues between the Company and SunEdison have been approved and authorized pursuant to this authority by those members of the Conflicts Committee in place at the time the applicable decision was made.
The Company is not a part of the SunEdison Bankruptcy and does not rely substantially on SunEdison for funding or liquidity. The Company continues to participate actively in the SunEdison Bankruptcy proceedings, and the SunEdison Bankruptcy will continue to have a negative impact on the Company given our complex relationship with SunEdison.
During the SunEdison Bankruptcy, SunEdison has not performed substantially as obligated under its agreements with us, including under sponsorship arrangements consisting of the various corporate level agreements put in place at the time of the Company’s IPO (collectively, the “Sponsorship Arrangement”) and certain O&M and asset management arrangements. SunEdison’s failure to perform substantially as obligated under its agreements with us, including under the Sponsorship Arrangement, project level O&M and asset management agreements and other support agreements may have a material adverse effect on the Company. Despite these adverse effects, the Company expects that it will be able to operate its business without the support of SunEdison pursuant to the plans for transitioning away from reliance on SunEdison that we are in the process of implementing. These plans include, among other things, establishing stand-alone information technology, accounting and other critical systems and infrastructure, directly hiring our employees, and seeking proposals for alternative O&M and asset management services for our power plants. In addition to the one-time costs of implementing a stand-alone organization, our business will be adversely affected to the extent we are unsuccessful in implementing the relevant plans or the resulting ongoing long-term costs are higher than the costs we are expecting to incur with SunEdison as a sponsor.
The project level financing agreements for our two remaining levered power plants in India and our three power plants in South Africa contain provisions that provide the lenders with the right to accelerate debt maturity due to the SunEdison Bankruptcy because SunEdison is an original sponsor of the project and/or a party to certain material project agreements, such as O&M and EPC related contracts. In addition, certain audited financial statements at the project level have been delayed, which may create or may have already created defaults at the project level for our levered power plants. If not cured or waived, these defaults may restrict the ability of the project companies to make distributions to us and may provide the lenders with the right to accelerate debt maturity. However, our corporate level revolving credit facility and the indenture governing our 9.75% Senior Notes due 2022 do not include an event of default provision triggered by the SunEdison Bankruptcy, and none of our power purchase agreements includes a provision that would permit the offtake counterparty to terminate the agreement as a result of the SunEdison Bankruptcy.

On September 25, 2016, the Company filed its initial proof of claim in the SunEdison Bankruptcy case, and filed an amended proof of claim on October 7, 2016. As set forth in the proofs of claim, the Company believes it has unsecured claims against SunEdison that it estimates are in excess of $2.0 billion. These claims include, without limitation, claims for damages relating to breach of SunEdison's obligations under the Sponsorship Arrangement between the Company and SunEdison and other agreements; contribution and indemnification claims arising from litigation; claims relating to SunEdison’s breach of fiduciary, agency and other duties; and claims for interference with and the disruption of the business of the Company and its subsidiaries, including the loss of business opportunities, loss of business records, failure to provide timely audited financials, and the increased cost of financing and commercial arrangements. Many of these claims are contingent, unliquidated and/or disputed by SunEdison and other parties in interest in the SunEdison Bankruptcy case, and the estimated amounts of these claims